Projects, and what actually happened
We'd rather show the detail than a logo wall. Here is what we delivered, what stood in the way, and where the site got to. Clients stay unnamed unless they've told us otherwise.
An urgent client request: a secure, resilient network in five weeks
A new decontamination facility needed a complete network installed quickly, ready for validation and an external audit, without cutting corners on security.
- 5 weeks approval to live
- 10 segregated networks
- 0 ports open from the internet
A state-of-the-art decontamination facility, from empty building to audit
A new super centre built from an empty shell: equipment, rooms, workflow and IT planned together, through validation of every machine to a Notified Body audit and go-live.
- Eleven workstreams
- Validation and audit readiness
- GO / NO-GO gates
Two legacy tracking systems onto one platform
A department running two separate instrument tracking systems, migrated onto Assure. Item and set data moved across without losing the history attached to it, which is the part that makes a migration hard.
- Two systems into one
- Item and set data migrated
- History preserved
An instrument tracking system off its on-premise server
A tracking system moved from a server sitting in a cupboard on site to hosting we run in the cloud, so the department stopped depending on a single box in a building.
- On-premise to cloud
- Service kept available
- Backed up and monitored
If you'd like a reference for a project like yours, ask us and we can usually put you in touch.
Want to talk to someone who has done this?
Tell us what you're planning and we'll share the closest project we've delivered, including what we'd do differently.